South Goa district hospital building to be handed over to DHS in phases in Dec: GSIDC

NT NETWORK

Margao

The South Goa’s district hospital project has missed yet
another deadline, and the building will now be handed over to the Directorate
of Health Services (DHS) in phases over
the month of December.

The reasons for the delay in the completion of the
hospital building are pending payments
to contractors and ‘indecision’ over the top two floors of the building.

The new plan of handing over the hospital building
emerged after an inspection was called for by the Committee on Public
Undertakings, headed by Margao MLA Digambar Kamat.

Kamat and committee members Cuncolim MLA Clafacio Dias and Nuvem MLA
Wilfred D’Sa besides Hospicio’s medical superintendent Dr Ira Almeida and Goa
State Infrastructure Development Corporation (GSIDC) officials were present
during the inspection.

Kamat while speaking to this daily said that the hospital
building would be completed in another month.

“We had the last meeting about the hospital in July where
we were told that the hospital would be commissioned by November, but it didn’t
happen. They have said they will try to complete it by November 30 provided the
contractors are given their payments. This hospital has to be taken on a
priority as it is a major requirement for South Goa,” he
said.

GSIDC’s general manager Jude Carvalho, who was also
present during the inspection, said that the main reason for the delay in the
handing over of the hospital building is the pending payments to contractors.

“95 per cent of the work is already completed, and 98 per
cent of the material is already come to the hospital. Payments have not been
given to the contractors; this has also led to a delay to some extent. Another
critical activity is that six OTs (operating theatres) are coming from Europe. They have been
shipped and are expected to reach by December 15. There are five other OTs that
are made in India. Once the contractor is paid, they will be installed. Till
then we will do the commissioning and testing of the rest of the hospital and
complete the handover in phases,” said Carvalho.

Uncertainty over the top two floors also played a part in
the delay in the completion of the hospital building.

Initially, the fourth and fifth floors were supposed to
house a nursing college, but later there was a change in the decision and it
was planned to turn it into a medical
college.

Recently, the GSIDC was asked to leave the two floors
vacant raising the question over the work already done.

This ‘confusion’ took away about a month and a half of
the hospital project’s timeframe.

Carvalho said that the hospital building would be
completed by the end of November and handed over to the Directorate of Health
Services (DHS) in phases during the month of December.

Source:: The Navhind Times

Leave a Reply

Your email address will not be published. Required fields are marked *